AHTS BLIZZARD returns to SHL

BLIZZARD ASSISTING WITH SYLWIN 1-PROJECT

Early April BLIZZARD will start an approximate 60 days contract with Seaway Heavy Lifting to assist with the installation of Sylwin I converter platform west of the German island Sylt.  The platform will be used as a ‘transmitter’ to connect offshore wind farm Dan Tysk with a receiver ashore. The 5800 tons jacket will be installed by HLV OLEG STRASHNOV. At a later stage the 14,000 tons transmission station will be installed by float-over.  From late February to mid March, BLIZZARD assisted in the towage of EIDE BARGE 33, loaded with the jacket, from Wismar to Eemshaven via Skaw.